Ford engineers at Bridgend plant have been trialling an assembly line with the auto industry’s first cardboard engine.
As the plant gears up for next year’s introduction of a new six-cylinder engine for the Premier Automotive Group, its prototype centre sent a cardboard box substitute down the production line.
Putting together a cardboard engine is part of the detailed production planning process now underway at Bridgend. The aim was to ensure maximum efficiency by ensuring the engine passes all points on the assembly line without fouling or sticking.
This novel approach is one of the many new techniques and working practices introduced by Bridgend’s prototype centre in the run-up to full production.
The new engine, known in the plant as I6, will be built on the same production line as the 4.4-litre V8 launched last year. This demands the hands-on approach demonstrated by the prototype centre to integrate six-cylinder production on the eight-cylinder assembly line.
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalDataBuild operators have also fine-tuned a miniature assembly line in Bridgend’s prototype centre where engines are hand-built for testing. Each engine is currently assembled by two-person teams in two shifts, but when it goes into full production in early 2006 the I6 will be rolling off line at a rate of thousands a week.
Plant manager Bob Murphy said: “Ideas can be tried out on our mini line first, before being taken to the full scale assembly line for verification. Or we can do the reverse – bring engines off the assembly line and test them in the prototype centre without interrupting production.”